Downtown drivers should plan for months of traffic changes as PennDOT tackles a $14.34 million flood control project along the Parkway East’s “bathtub.” Crews are raising the floodwall, replacing pavement and upgrading drainage systems between Grant Street and the Fort Pitt Bridge, with work expected to finish in fall 2027.

Through August 2027, restrictions include a westbound left-lane closure, closures of the Grant Street on-ramp and Stanwix Street off-ramp, and a shorter exit lane to the Fort Duquesne Bridge. A 12-day full westbound closure is also planned for 2027, with dates still to be announced. Eastbound traffic is not expected to be restricted.

Drivers traveling through Downtown Pittsburgh face months of lane restrictions and ramp closures as PennDOT undertakes a $14.34 million project to reduce flooding along the Parkway East’s notorious “bathtub” section.

The project covers westbound I-376 between the Grant Street interchange and the Fort Pitt Bridge. Construction began in October and is expected to continue through fall 2027, with Golden Triangle Construction Company serving as the prime contractor.

Crews will reconstruct and raise 1,150 feet of floodwall, replace the roadway pavement and upgrade pumps and piping. The work also includes installing micropiles to strengthen the foundation beneath the highway. Monongahela Wharf parking areas will be affected during construction.

The low-lying stretch beside the Monongahela River has experienced increasingly frequent flooding closures over the past decade. PennDOT says each closure diverts approximately 43,000 vehicles and requires crews to pump out water and remove mud and debris before traffic can return. The improvements are intended to reduce flooding and help crews respond more efficiently when it occurs.

Traffic restrictions through August 2027

PennDOT scheduled the following around-the-clock restrictions to begin Oct. 3 and remain in place through August 2027:

* Grant Street: The on-ramp to westbound I-376 is closed. The westbound exit to Grant Street remains open.
* Stanwix Street: The westbound off-ramp is closed. The Stanwix Street entrance to westbound I-376 remains open.
* Westbound Parkway East: The left lane is closed between the Grant Street entrance ramp and the Stanwix Street entrance ramp.
* Fort Duquesne Bridge exit: The exit lane is shortened to maintain two through lanes toward the Fort Pitt Bridge.

Drivers who normally enter from Grant Street are directed along Fort Pitt Boulevard to the Stanwix Street entrance. Drivers heading to Stanwix Street from westbound I-376 should exit at Grant Street and follow Fort Pitt Boulevard.

No project-related lane restrictions are anticipated on eastbound I-376 in this corridor.

## A 12-day closure ahead.

A full closure and detour of the westbound bathtub section is planned during the 2027 construction season so crews can replace the pavement across the roadway’s full width. PennDOT’s announcement does not specify the dates.